Thursday, June 14, 2012

Bathroom Construction: End of Day 20

The plumber came on Monday (which was day 20) and hooked up all the new copper to the actual water supply, though the actual fittings won't be installed until the drywall is on. Mortar support underneath the tub was also placed. The general contractor dropped off supplies to install the vents for the dryer and bathroom, but didn't actually install them. Additionally it was my birthday, so I took the day off from construction and had a wonderful time.

No comments: